What is the process of keeping actual costs and the planned budget in-line?

  1. Pinching
  2. Control Costs
  3. Squeeze down
  4. Mitigate

Answer(s): B



Which Team Member is responsible for ensuring the Project team is aware of Constraints?

  1. Sponsor
  2. Supplier
  3. Accountant
  4. Coordinator

Answer(s): A



During the Execution phase, a Stakeholder makes a product feature enhancement. This is an example of which type of Scope Creep?

  1. Top-down
  2. Perfectionism
  3. Unexpected
  4. Placating

Answer(s): D



Which Technical Skills are Career Path Core Competencies of a Project Director?

  1. Evaluates and redesigns practice offerings
  2. Understands the implications of different technical choices and is able to guide our clients to the best solution for their situation
  3. Only (a)
  4. Both (a) and (b)

Answer(s): C