The defining characteristic of a Project is that its outcomes are unique.

  1. TRUE
  2. FALSE

Answer(s): A



Which is not a main Life cycle phase?

  1. Managing and Costing
  2. Initiating
  3. Closing
  4. Executing

Answer(s): A



Which Stakeholder is considered “the workhorses of the team.”?

  1. Project Director
  2. Team Member
  3. Project Manager
  4. Key Team Member

Answer(s): B



What type of Scope Creep is when a team member adds an unplanned feature to a product?

  1. Projecting
  2. Perfecting
  3. Striving
  4. Placating

Answer(s): B



Which of the following is not considered as a stakeholder?

  1. Sponsor
  2. Owner
  3. Project Director
  4. None of the Above
  5. Both (a) and (b)
  6. Both (a) and (c)

Answer(s): D