Which statement below best describes the primary objective of the Sprint Retrospective?

  1. The primary objective of the Sprint Retrospective is to identify what went wrong or hindered the Sprint
  2. The primary objective of the Sprint Retrospective is to provide feedback to the Product Owner(s).
  3. The primary objective of the Sprint Retrospective is to recommend ways to work better in the
    Sprint

Answer(s): C



Which of the following is not reflected in a Sprint Burn down Chart?

  1. Total Days in Sprint
  2. Number of Tasks Remaining
  3. Day of Sprint
  4. Work Hours Remaining

Answer(s): B



What artifact shows actual versus planned progress?

  1. What artifact shows actual versus planned progress?
  2. Burn down Chart
  3. Task Breakdown

Answer(s): B



Which of the following is NOT part of the Sprint?

  1. The product is released to customers after each Sprint
  2. The principal goal for a Sprint is to produce release-quality increments in functionality
  3. Releases usually incorporate the result of multiple Sprints
  4. Occur at times dictated by customer and business needs

Answer(s): A