You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information:
Sprint 1: 10 pontos
Sprint 2: 11 pontos
Sprint 3: 15 pontos
Sprint 4: 14 pontos
Sprint 5: 15 pontos
Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?

  1. 6
  2. 5
  3. 4
  4. 3

Answer(s): B



Under what circumstances should the Product Backlog be reprioritized?

  1. The Scrum Master should reprioritize the Product Backlog only at the end of a new Sprint
  2. The Scrum Master should reprioritize the Product Backlog only at the beginning of a new Sprint
  3. The Team should reprioritize the Product Backlog only at the end of a new Sprint.
  4. The Product Owner should reprioritize the Product Backlog whenever new information is learned

Answer(s): D



How could the team and other stakeholders know if a product backlog item is done?

  1. They should ask to the member's development team
  2. They should compare what was done, against the definition of Done established by the Scrum Team
  3. Ask to the Product Owner
  4. Ask to the Manager

Answer(s): C



What is the primary objective of the daily scrum?

  1. To share with the team what each member has completed in the Sprint, what each member will work on next, and to report progress roadblocks
  2. To give a status report to the Product Owner on what each member has completed in the Sprint, what each member will work on next, and to report progress roadblocks.
  3. To discuss work details with the team since every team member must attend the meeting
  4. To give a status report to the Scrum Master on what each member has completed in the Sprint, what each member will work on next, and to report progress roadblocks.

Answer(s): A