You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?
Answer(s): A
Which statement below best describes the primary objective of the Sprint Retrospective?
Answer(s): C
Which of the following is not reflected in a Sprint Burn down Chart?
Answer(s): B
What artifact shows actual versus planned progress?
Which of the following is NOT part of the Sprint?
Post your Comments and Discuss GAQM CSM-001 exam prep with other Community members:
Our website is free, but we have to fight against AI bots and content theft. We're sorry for the inconvenience caused by these security measures. You can access the rest of the CSM-001 content, but please register or login to continue.