Who determines whether the development team has been assigned enough work in a Sprint?

  1. The Development Team
  2. The Product Owner
  3. The Product Owner and the Scrum Master
  4. The Scrum Master

Answer(s): A



Which of the following items is not a Product Owner responsibility?

  1. Maintaining the Product Backlog with current information
  2. Working with stakeholders to determine and detail product features
  3. Assigning tasks to team members
  4. Prioritizing the Product Backlog

Answer(s): C



Which of the following activities do not occur at the end of the Sprint?

  1. Software development
  2. Release deployment
  3. Sprint review meeting
  4. Quality assurance testing

Answer(s): A,D



What does the Scrum Development Team attempt to develop every Sprint?

  1. A product that is ready for customer delivery
  2. A completed Sprint Backlog
  3. A product that is ready for QA and/or QC testing
  4. A product increment that is potentially-ready for customer delivery

Answer(s): D