Which of the following is reflected in a Sprint Burn down Chart?

  1. Team Members Name
  2. Number of Product Backlog Items Completed
  3. Number of Tasks Remaining
  4. Work Hours Remaining

Answer(s): D



How many hours per day should a person on a Scrum team work?

  1. A sustainable pace, usually from 7-8 hours per day.
  2. An "ideal day" measuring only when he or she is productive.
  3. However many hours are needed to get the work done.
  4. 14 hours.

Answer(s): A



According to Scrum, the amount of time for a team to plan Sprint activities is expressed in what unit of time?

  1. Weeks
  2. Days
  3. Hours
  4. Minutes

Answer(s): C



You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information:
Sprint 1: 10 pontos
Sprint 2: 11 pontos
Sprint 3: 15 pontos
Sprint 4: 14 pontos
Sprint 5: 15 pontos
Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?

  1. 6
  2. 5
  3. 4
  4. 3

Answer(s): B



Under what circumstances should the Product Backlog be reprioritized?

  1. The Scrum Master should reprioritize the Product Backlog only at the end of a new Sprint
  2. The Scrum Master should reprioritize the Product Backlog only at the beginning of a new Sprint
  3. The Team should reprioritize the Product Backlog only at the end of a new Sprint.
  4. The Product Owner should reprioritize the Product Backlog whenever new information is learned

Answer(s): D