A project manager for a small construction company has a project that was budgeted for US $130,000 over a six-week period. According to her schedule, the project should have cost US $60,000 to date. However, it has cost US $90,000 to date. The project is also behind schedule, because the original estimates were not accurate.
Who has the PRIMARY responsibility to solve this problem?
- Project manager
- Senior management
- Project sponsor
- Manager of the project management office