You are the project manager on an information technology project on which you and the sponsor have already approved the scope. An information specialist on your team, after having lunch with a low ranking customer representative working with him on a software project, learns that a simple alteration in the display would be a great addition to the project. The information specialist installs the change with no negative effect on the project schedule and at no additional cost. What action should be taken?
Answer(s): C
Which of the following is NOT included in a schedule change control system?
Answer(s): D
Which of the following is generally the MOST CORRECT use of a project network diagram?
Answer(s): B
In an activity-on-node diagram,the nodes represent:
A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. Which activities have float available?
Answer(s): A
Post your Comments and Discuss GAQM PPM-001 exam dumps with other Community members:
No discussions yet for this exam. Be the first to share your experience and help others prepare!
💬 Did you find this helpful?
Thank you for sharing! Your feedback helps the community.