Huawei H12-425 Exam
HCIP-Data Center Facility Deployment V1.0 (Page 5 )

Updated On: 1-Feb-2026

The video can be viewed on NetEco only after the video camera is configured on the IVS

  1. TRUE
  2. FALSE

Answer(s): A



Commissioning UPS5000-E parallel system, the reason for triggering EPO ports is (___________________).

  1. To protect loads against electric shock and ensure safety
  2. To power off the loads and prevent damage to the loads.
  3. To protect batteries and prevent battery discharge
  4. To disconnect the output and set the parallel parameters

Answer(s): B



In direct ventilation mode, the direct ventilation system exchanges heat between outdoor cool air and indoor hot air.

  1. TRUE
  2. FALSE

Answer(s): A



The NetCol5000-C indoor fan generates a loud noise, the possible reasons ( ).

  1. The air filter is dirty or blocked.
  2. The fan air exhaust vent is dirty or blocked
  3. The fan is not securely installed
  4. The fan is faulty

Answer(s): A,B,C,D



If UPS5000-E is ( ), setting wizard automatically starts after power-on.

  1. Powered on for the first time
  2. Powered on after power-off
  3. Powered on after factory settings are restored.
  4. Powered on after faults are rectified

Answer(s): A,C



Viewing page 5 of 49
Viewing questions 21 - 25 out of 240 questions



Post your Comments and Discuss Huawei H12-425 exam prep with other Community members:

Join the H12-425 Discussion