A system is configured with 15min battery backup time, and the discharge termination voltage of the battery cell should be selected ( ). /

  1. 1.75V
  2. 1.80V
  3. 1.67V
    D .1.60V

Answer(s): C



A project requires the management system to be connected to two third-party generator sets (same model) 1 ATS (same model), six precision air conditioners (same model), and five smart meters (same model), then the management system Need to report () a third- party device access fee? ()

  1. 3
  2. 10
  3. 14
  4. None of the above is true

Answer(s): D



A project requires the management system to access a third-party generator set, two smart meters 1 (same model), and two precision air conditioners (same model), then the management system needs to report () a third-party equipment access fee ? (

  1. 1
  2. 3
  3. 5
  4. None of the above is true

Answer(s): B



If a project needs the management system to monitor the PUE value of the room, what function does NetEco need to quote separately?

  1. No separate quotation is required
  2. Capacity Management
  3. Mobile APP
  4. Energy Efficiency Management

Answer(s): D



In a project that requires the deployment of three-layer temperature cloud maps in high-density areas, it is necessary to deploy () temperature probes in each cabinet?

  1. 2
  2. 6
  3. 3
  4. 4

Answer(s): B