A deployment professional just installed new QRadar deployment which comes with a temporary license key.
How many days does a deployment professional have before the temporarylicensekey expires?

  1. 35 days from the installation date.
  2. 15 days from the installation date.
  3. 30 days from the installation date.
  4. 45 days from the installation date.

Answer(s): C



A deployment professional needs to implement a crossover cable in the high availability (HA) environment. By doing so, this QRadar deployment isolates what kind of traffic over the crossover connection?

  1. event
  2. flow
  3. query
  4. HA replication

Answer(s): A



A deployment professional is asked to create QRadar deployment architecture for a company.
The company has three branch offices with WAN connection between them. The head office data center requires 14000 EPS and 200000 FPM. Each branch requires 4000 EPS and 200000 FPM.
Which deployment solution will meet the minimum requirements?

  1. QRadar 3105 (Console) in head office + QRadar 1805 Event and Flow Processor in each branch office
  2. QRadar 3129 (Console) in head office + QRadar 1805 Event and Flow Processor in each branch office
  3. QRadar 3105 (Console) and QRadar Event and Flow Processor 1829 in head office + QRadar 1805 Event and Flow Processor in each branch office
  4. QRadar 3129 (All-in-One) in head office

Answer(s): A



A deployment professional configures QRadar auto-update with the automatic install option for all update types where automatic install is available.
Assuming all auto-update installations are successful, which update types will need manual installation?

  1. Major updates, scanner and protocol updates
  2. Configuration updates and WinCollect updates
  3. Application updates and major updates
  4. Application updates, DSM, scanner and protocol updates

Answer(s): D