When performing a quality audit engagement in a factory, an internal auditor should first review

  1. Comparisons of actual outputs to planned outputs.
  2. Levels of rework and scrap.
  3. Costs of materials purchased.
  4. Fulfillment of production quotas.

Answer(s): B



An auditor evaluating excessive product rejection rates should investigate

I). Communication between sales and production departments on sales returns.
II). Volume of product sales year to date in comparison to prior year to date.
III). Changes in credit ratings of customers versus sales to those customers.
IV). Detailed product scrap accounts and accumulations.

  1. I and III only.
  2. I and IV only.
  3. II, III, and IV only.
  4. I, II, III, and IV.

Answer(s): B



An internal audit activity is participating in the due diligence work for an acquisition that a company is considering. One engagement objective is to determine if the acquisition's accounts payable contain all outstanding liabilities. Which of the following audit procedures would not be relevant for this objective?

  1. Examine supporting documentation of subsequent (after period) cash disbursements and verify period of liability.
  2. Send confirmations, including zero balance accounts, to vendors with whom the company normally does business.
  3. Select a sample of accounts payable from the accounts payable list and verify the supporting receiving reports, purchase orders, and invoices.
  4. Trace receiving reports issued before the period end to the related vendor invoices and accounts payable list.

Answer(s): C



A company has recently incurred significant cost overruns on one of its construction projects. Management suspects that these overruns were caused by the contractor improperly accounting for costs related to contract change orders. Which of the following procedures would be appropriate for testing this suspicion?

I). Verify that the contractor has not charged change orders with costs that have already been billed to the original contract.
II). Determine if the contractor has billed for original contract work that was canceled as a result of change orders.
III). Verify that the change orders were properly approved by management.

  1. I only.
  2. III only.
  3. I and II only.
  4. I and III only.

Answer(s): C



As part of an operational audit, an auditor compared records of current inventory with usage during the prior two year period and determined that the spare parts inventory was excessive. What step should the auditor perform first?

  1. Determine the effects of a stock-out on the organization's profitability.
  2. Determine whether a clear policy exists for setting inventory limits.
  3. Determine who approved the purchase orders for the spare parts.
  4. Determine whether purchases were properly recorded.

Answer(s): B