Free IIA IIA-CIA-Part3 Exam Braindumps (page: 76)

Assume that C Company offers to perform the operation 2 function on 1,000 units at a unit price of US $40, excluding direct materials cast. Also assume that Y Company offers to perform the Operation 1 function an 1,000 units at a unit price of US $7, excluding direct materials cost.
Which of these mutually exclusive offers is acceptable?

  1. C but not Y.
  2. Y but not C.
  3. X or Y.
  4. Neither offer should be accepted.

Answer(s): A

Explanation:

KG's offer should be accepted because its cast is US $40,000 1,000 units x $40), but the increase in throughput contribution is US $72,000 [1,000 units $120 unit price -- $48 E' 1 per unit)]. Hence, the relevant cost of QC's offer is less than the incremental throughput contribution. ms's offer effectively increases the capacity of the bottleneck operation. Y's offer should be rejected because, even though its US $7 unit price is less than the US $8 unit operating cost excluding direct materials) for Operation 1. it will result in the incurrence of additional casts with no increase in throughput contribution, given that Operation 2 is already producing at its 150,000-unit capacity.



Company J produces two components: A-1 and A-2. The unit throughput contribution margins for A-1 and A-2 are US $150 and US $300, respectively. Each component must proceed through two processes: Operation 1 and Operation 2. The capacity of Operation 1 is 180 machine hours, with A-1 and A-2 requiring 1 hour and 3 hours, respectively.
Furthermore, Company J can sell only 45 units of A-1 and 100 units of A-2. However,
Company J is considering expanding Operation 1's capacity by 90 machine hours at a cost of US $80 per hour. Assuming that Operation 2 has sufficient capacity to handle any additional output from Operation 1, how much should Company J produce?

  1. Option A
  2. Option C
  3. Option C
  4. Option D

Answer(s): C

Explanation:

A-1's throughput contribution margin per unit of the scarce resource the internal binding constraint) is US $150 $150 UCM - 1 machining hour). A-2's throughput contribution margin per unit of the scarce resource is U $100 $300 UCM - 3 machine hours).
Consequently, Company J should produce as much A-1 as it can sell 45 units). If Company adds 90 machine hours to increase the capacity of Operation -I to 270 hours 180 + 90), it cannot produce additional units of A-1 because the external binding constraint has not been relaxed. However, it can produce additional units of A-2. Given that the UCM per machine hour of A-2 is U $100 and that the cost is US $80 per hour, adding capacity to Operation 1 is profitable. Thus, Company J should use 45 machine hours to produce 45 units of A-1. The remaining 225 machine hours 270 - 45) should be used to produce 75 units 225 - 3 hours) of A-2. The latter amount is within the external binding constraint. A company produces two products, and Y, which use material and labor as inputs. Fixed amounts of labor and material are available for production each month In addition. the demand for product Y each month is limited: product has no constraint an the number of units that can be sold. A graphical depiction of these production and demand constraints is presented in the opposite column.



The feasible solution region is bounded by the lines connecting points:

  1. 3, 4, 6, and 7.
  2. I, 5, 6, and 8.
  3. 2, 4, , , and 8.
  4. 3, E. 6, and 7.

Answer(s): A

Explanation:

A model consisting of a system of functions may be used to optimize an objective function. If the functions in the model are all linear, the model is a linear programming model. Linear programming is a technique to determine optimal resource allocation. Several solution methods are available to solve linear programming problems. The graphical method, the easiest technique, is limited to simple problems. Here, the graph consists of three lines, each representing a production constraint. The lines connecting points , 4, 6, and 7 bound the feasible solution region. Product mikes of and Y that lie outside this boundary cannot be produced and/or sold because the demand constraint line ,4), the labor constraint line 4,6), and the material constraint line 6,7) are binding. A company produces two products, and Y, which use material and labor as inputs. Fixed amounts of labor and material are available for production each month In addition. the demand for product Y each month is limited: product has no constraint an the number of units that can be sold. A graphical depiction of these production and demand constraints is presented in the opposite column.



If a series of profit lines for and Y are drawn on the graph, the mix of G and Y that will result in the maximum profit can be determined from:

  1. The last point in the feasible solution region touched by a profit line.
  2. Any point on the boundary of the feasible solution region touched by a profit line.
  3. The first paint an the feasible solution region boundary that intersects a profit line.
  4. Any point on the demand constraint that intersects a profit line.

Answer(s): A

Explanation:

A profit line has negative slope because the profit from sales of one product increases as the profit from sales of the other product declines. Moving the profit line rightward while maintaining its slope) to the last paint in the feasible region determines the solution.



Viewing page 76 of 390
Viewing questions 301 - 304 out of 1555 questions



Post your Comments and Discuss IIA IIA-CIA-Part3 exam prep with other Community members:

IIA-CIA-Part3 Exam Discussions & Posts