What portion of the communications model could be defined as the translator?

  1. Receiver
  2. Medium
  3. Translator
  4. Sender

Answer(s): B



Which of the following is derived from a schedule model to meet the project execution plan and achieve management approval for use as a baseline?

  1. Updating
  2. Impacts
  3. Baseline schedule
  4. Dumping

Answer(s): C



The_____________, an output of the define scope process, does document the process and criteria for accepting completed products.

  1. Statement of Work
  2. Contract
  3. Project scope statement
  4. Project management plan

Answer(s): C



Which of the following requires that all parties in the conflict must give up something?

  1. Barrier
  2. Problem solving
  3. Withdrawal
  4. Compromising

Answer(s): D



Which of the following defines how the project scope should be created, executed, monitored and controlled, and then validated?

  1. Scope variance plan
  2. Scope management plan
  3. Staffing management plan
  4. Schedule management plan

Answer(s): B