Which of the following describes the organizational policies, procedures, forms, and methodologies the business analyst is to follow?

  1. Organizational process asset
  2. Enterprise architecture
  3. Business need
  4. Matrix structure

Answer(s): A

Explanation:

Organizational process assets describe the organizational policies, procedures, forms, and methodologies the business analyst is to follow.
Answer C is incorrect. The business need describes business requirements, solution scope, and solution requirements.
Answer B is incorrect. The enterprise architecture describes the relationship among the organizational units and how the organizational units act with one another. Answer D is incorrect. A matrix structure is not one of the three inputs to the business analysis process.



You are the business analyst for your organization. You've believed that your solution can actually be purchased from outside vendor rather than trying to create the solution internally. You decide to ask the vendor to provide a fee for their services based on the statement of work.
What document will you give the vendor along with the statement of work?

  1. Request for quote
  2. Contract terms
  3. Request for proposal
  4. Purchase order

Answer(s): A

Explanation:

When an organization wants just the cost of the service or product, request for quote is used. Quotes, provided by vendors to buyers, don't present any ideas or direction, but provide just the cost of the solution.
Answer C is incorrect. Request for proposal asks the vendor to provide detail on a proposed solution and the cost of the solution.
Answer D is incorrect. Purchase order tells the vendor that your organization will be purchasing the goods or services.
Answer B is incorrect. Contract terms aren't feasible, as the business analyst doesn't know how much the solution will cost. Contract terms come later in the procurement process.



Which requirements allocation technique is best described as the breaking down of the solution scope into smaller units for allocation?

  1. Functional decomposition
  2. Resource allocation granularity
  3. WBS creation
  4. Process modeling

Answer(s): A

Explanation:

Functional decomposition takes the solution scope and decomposes it into smaller, more manageable units. Answer B is incorrect. Resource allocation granularity isn't a business analysis term and is not acceptable for this Question.
Answer D is incorrect. Process modeling maps activities in a process model to different roles, vendors, and contractors.
Answer C is incorrect. WBS creation also uses a decomposition of the project scope into work packages, but it's not the process described in this Question.



John and Hanna are business analysts in their organization and they are completing the verification activities to check for completeness of the requirements.
When should John and Hanna perform these verification activities?

  1. At each milestone of the requirements analysis process
  2. Once all of the requirements have been gathered
  3. Iteratively throughout the requirements analysis process
  4. As often as the requirements management plan calls for

Answer(s): C

Explanation:

Requirements verification activities are performed iteratively throughout the requirements analysis process. Answer A is incorrect. Requirements verification happens in iterations, not just at milestones (assuming there are milestones in the process). Answer B is incorrect. Verification activities don't happen just at the end of the requirements gathering process, but iteratively throughout the process. Answer D is incorrect. This answer is tempting, but it's not the best answer.



Page 14 of 129



Post your Comments and Discuss IIBA CCBA exam with other Community members:

Mohammed Basheer commented on August 23, 2017
Wrote the exam today and I passed it easily. Valid dump!
UNITED STATES
upvote