Which approach to business analysis activities deals with rapid delivery of the business value?

  1. Quality-driven
  2. Change-driven
  3. Plan-driven
  4. Stakeholder-driven

Answer(s): B

Explanation:

Change-driven approaches to business analysis deal with rapid delivery of the business value. The business value is delivered in short iterations in return for acceptance of a higher degree of uncertainty regarding the overall delivery of the solution. The change-driven approaches are preferred while taking an exploratory approach for incremental improvement of an existing solution. Answer C is incorrect. The plan-driven approach defines business analysis activities. This approach is used to focus on minimizing up-front uncertainty and to ensure that the solution is fully defined before implementation begins in order to maximize control and minimize risk. It is preferred when requirements are effectively defined in advance of implementation. Answer A is incorrect. The quality-driven approach is not a valid defined approach to business analysis activities.
Answer D is incorrect. This is not a valid defined approach for the CCBA examination.



Fred is the business analyst for his organization. His current initiative is quite large, so Fred decides to create a high-level plan for the business analysis approach, and then to create a detailed plan for the most imminent activities.
What type of business analysis planning is Fred using in this scenario?

  1. Step planning
  2. Iterative planning
  3. Cyclic planning
  4. Rolling wave planning

Answer(s): D

Explanation:

This is an example of rolling wave planning. This approach to planning is ideal for larger business analysis initiatives and allows the business analyst to plan the entire initiative and approach at the high-level and the most imminent activities at the detailed level. Answer B is incorrect. Iterative planning is not a valid choice; planning does happen in iterations with the rolling wave planning approach, but it's not the correct name for the approach. Answer A is incorrect. Step planning is not a valid term for business analysis processes. Answer C is incorrect. Cyclic planning isn't a valid term for the described rolling wave planning.



As a business analyst, you'll need to communicate with the stakeholders of the solution you propose.
Why is it important for the business analyst to review the stakeholder concerns as part of the assessment of the organization for the readiness of the solution?

  1. To gain confidence and synergy among the stakeholders
  2. To confirm stakeholder prioritization
  3. To confirm the stakeholders' commitment of the solution
  4. To address potential problems or issues

Answer(s): D

Explanation:

Stakeholder concerns can magnify to problems and issues with the implementation of the solution.

It's best to address these concerns, issues, threats, and perceived threats before the actual transition to the new solution. Answer C is incorrect. This isn't the best answer for the Question as the stakeholders are already committed to the solution if they've approved the solution scope. Answer B is incorrect. Stakeholder prioritization isn't an activity at this point of business analysis duties. Requirements have already been prioritized and presented in the solution scope. Answer A is incorrect.
While it's ideal to create synergy among the stakeholders, this input is really addressing any issues or perceived threats.



As a business analyst, you should work to identify opportunities to improve the operations of your organization.
Which one of the following improvement opportunities aims to improve the experience of the customer?

  1. Eliminate redundancy.
  2. Automate or simplify the work people perform.
  3. Increase consistency of behavior.
  4. Improve the purchasing process.

Answer(s): C

Explanation:

When customers experience the same process, such as checkout in different ways, it's frustrating. This improvement opportunity aims to create consistency in all behaviors to improve the customer experience. Answer B is incorrect. Automating or simplifying the work people perform helps streamline costs and improve quality by doing the work in the same way each time the work is performed.
Answer A is incorrect. Eliminating redundancy considers that stakeholders may have common needs that can be met with a single solution, reducing the cost of implementation. Answer D is incorrect.
While this choice is tempting, it's not an actual improvement opportunity for the business analyst to consider.



Page 32 of 129



Post your Comments and Discuss IIBA CCBA exam with other Community members:

Mohammed Basheer commented on August 23, 2017
Wrote the exam today and I passed it easily. Valid dump!
UNITED STATES
upvote