IIBA IIBA-AAC Exam
Agile Analyst (Page 5 )

Updated On: 26-Jan-2026

A team member has written a full user guide about a feature that has not yet been developed. Shortly before delivery is to start, the feature is dropped. What did the team member forget to value highly?

  1. Following the plan
  2. Detailed processes
  3. Fixed iterations
  4. Working solutions

Answer(s): D


Reference:

https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf (17)



When the product owner determines there has been enough value delivered on the initiative to satisfy the need, then the sponsor’s immediate next step is to:

  1. Cancel future work on the initiative to avoid waste
  2. Start work on the list of enhancements to improve the delivered product
  3. Hold individual interviews to collect feedback
  4. Dive deeper into the next delivery cycle’s stories

Answer(s): D



All team members participate at a review of their delivery process for the past 2 weeks. They consider issues, both pro and con, that influenced how much the team got done, as well as what they can do to make that better. This meeting is an example of the principle:

  1. Understand what is doable
  2. Iteration and progression
  3. Avoid Waste
  4. Stimulate collaboration and continuous improvement

Answer(s): A


Reference:

https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf (20)



The team realizes it is important that solution components are analyzed:

  1. In great detail so as much information as possible is available for subsequent work
  2. To provide answers to any potential questions from senior management
  3. So enough information is available to meet all stakeholder needs
  4. To a level of precision that is just enough to make an informed next decision

Answer(s): D


Reference:

https://www.agilealliance.org/wp-content/uploads/2017/08/AgileExtension_V2-Member-Copy.pdf (44)



The team is making important decisions when assessing the initiative they are working on. Feedback received from the Delivery Horizon informs:

  1. Priority and sequencing of solution components
  2. Identification of reporting requirements
  3. Suggestions for team process continuous improvement
  4. How to build the required solution components

Answer(s): A



Viewing page 5 of 18