Free COBIT5 Exam Braindumps (page: 6)

Page 5 of 41

In what order would the following outputs of the COBIT 5 Goals cascade mechanism be produced?

1. Enterprise Goals
2. Stakeholder needs
3 Enabler Goals
4. IT-related Goals

  1. 2, 1, 4, 3
  2. 1, 2, 3, 4
  3. 2. 3, 1, 4
  4. 3, 2, 4, 1

Answer(s): A



Who is an internal stakeholder?

  1. Shareholder
  2. Regulator
  3. Business process owner
  4. Business partner

Answer(s): C



Which aspect relates to the COBIT 5 principle 'Meeting Stakeholder Needs?

  1. Aligns with the latest views on Governance
  2. Translates stakeholder requirements into strategy
  3. Provides a simple architecture
  4. Defines relationship between Governance and Management

Answer(s): B



What is the name of the Change Enablement life cycle Phase which supports Phase 4. What needs to be done?

  1. Identify role players
  2. Define target state
  3. Plan program
  4. Define problems and opportunities

Answer(s): A






Post your Comments and Discuss ISACA COBIT5 exam with other Community members: