You are the project manager of your enterprise. You have identified several risks. Which of the following responses to risk is considered the MOST appropriate?

  1. Any of the above
  2. Insuring
  3. Avoiding
  4. Accepting

Answer(s): A

Explanation:

The appropriate response to the risk is decided by the risk itself, the company's attitude and appetite of risk, and the threat and opportunity combination of the risk.

Incorrect Answers:
B, C, D: Depending upon the condition, that is, the risk itself, the company's attitude and appetite of risk, and the threat and opportunity combination of the risk, these response options can be chosen.



John is the project manager of the HGH Project for her company. He and his project team have agreed that if the vendor is late by more than ten days they will cancel the order and hire the NBG Company to fulfill the order. The NBG Company can guarantee orders within three days, but the costs of their products are significantly more expensive than the current vendor. What type of response does John adopt here?

  1. Contingent response strategy
  2. Risk avoidance
  3. Risk mitigation
  4. Expert judgment

Answer(s): A

Explanation:

As in this case John and his team mates have pre-planned the alternative if the vendor would late in placing the order. Therefore, it is contingent response strategy.

Contingent response strategy, also known as contingency planning, involves adopting alternatives to deal with the risks in case of their occurrence. Unlike the mitigation planning in which mitigation looks to reduce the probability of the risk and its impact, contingency planning doesn't necessarily attempt to reduce the probability of a risk event or its impacts. Contingency comes into action when the risk event actually occurs.

Incorrect Answers:
B: Risk avoidance is the method which involves creating solutions that ensure a specific risk in not realized.

C: Risk mitigation attempts to eliminate or significantly decrease the level of risk present. Here no alternatives are pre-planned.

D: Expert judgment is utilized in developing risk responses, including feedback and guidance from risk management experts and those internal to the project qualified to provide assistance in this process.



You work as a project manager for BlueWell Inc. You are preparing for the risk identification process. You will need to involve several of the project's key stakeholders to help you identify and communicate the identified risk events. You will also need several documents to help you and the stakeholders identify the risk events. Which one of the following is NOT a document that will help you identify and communicate risks within the project?

  1. Stakeholder registers
  2. Activity duration estimates
  3. Activity cost estimates
  4. Risk register

Answer(s): D

Explanation:

Risk register is not an input to risk identification, but it is an output of risk identification. Incorrect Answers:
A, B, C: These are an input to risk identification.

Identify Risks is the process of determining which risks may affect the project. It also documents risks' characteristics. The Identify Risks process is part of the Project Risk Management knowledge area. As new risks may evolve or become known as the project progresses through its life cycle, Identify Risks is an iterative process. The process should involve the project team so that they can develop and maintain a sense of ownership and responsibility for the risks and associated risk response actions. Risk Register is the only output of this process.



You work as a project manager for TechSoft Inc. You are working with the project stakeholders on the qualitative risk analysis process in your project. You have used all the tools to the qualitative risk analysis process in your project. Which of the following techniques is NOT used as a tool in qualitative risk analysis process?

  1. Risk Urgency Assessment
  2. Risk Reassessment
  3. Risk Data Quality Assessment
  4. Risk Categorization

Answer(s): B

Explanation:

You will not need the Risk Reassessment technique to perform qualitative risk analysis. It is one of the techniques used to monitor and control risks.

Incorrect Answers:
A, C, D: The tools and techniques for Qualitative Risk Analysis process are as follows:
Risk Probability and Impact Assessment: Risk probability assessment investigates the chances of a particular risk to occur.
Risk Impact Assessment investigates the possible effects on the project objectives such as cost, quality, schedule, or performance, including positive opportunities and negative threats.
Probability and Impact Matrix: Estimation of risk's consequence and priority for awareness is conducted by using a look-up table or the probability and impact matrix. This matrix specifies the mixture of probability and impact that directs to rating the risks as low, moderate, or high priority.
Risk Data Quality Assessment: Investigation of quality of risk data is a technique to calculate the degree to which the data about risks are useful for risk management.
Risk Categorization: Risks to the projects can be categorized by sources of risk, the area of project affected and other valuable types to decide the areas of the project most exposed to the effects of uncertainty.
Risk Urgency Assessment: Risks that requires near-term responses are considered more urgent to address.
Expert Judgment: It is required to categorize the probability and impact of each risk to determine its location in the matrix.



Page 91 of 451



Post your Comments and Discuss ISACA CRISC exam with other Community members:

Fei commented on November 26, 2024
Very good resources
UNITED STATES
upvote

Yingying Li commented on December 02, 2023
Very useful practice tests.
Anonymous
upvote

Stephen commented on August 27, 2023
Can you please share CIMAPRA19-FO2-1 Exam dumps please
Anonymous
upvote

Parsad commented on June 04, 2023
Thank you for the buy 1 get 1 free discount. This helped me a lot. I donot have a lot of money.
INDIA
upvote

Petros commented on May 01, 2023
I could not have passed my certification test without the help of this study guide - highly recommend it!
PORTUGAL
upvote

Bobby commented on January 18, 2022
Passed easily.
UNITED STATES
upvote

Santosh commented on January 29, 2020
Passed my exam today with a score of 798. This is good material.
INDIA
upvote

Arron commented on January 26, 2020
This saved me so much time. The questions and answers are adequate and close to real exam. I like the PDF and its format. Just put it on my iPad and studied while traveling to work. This was my first time using this site and I am pretty happy about their service and price.
GERMANY
upvote

Suresh commented on April 17, 2019
This download is a waste of time . I downloaded the windows app and installed and it is asking to load the test. No documentation provided on how to use the desk top tool. Unable to install on my MAC not Iphone compatible. RE- Admin: Suresh, our website clearly says that the Test Engine software is for Windows only. We have not advertised anywhere in our website saying the Test Engine Software is for MAC as well.
UNITED STATES
upvote