For a large software development project, risk assessments are MOST effective when performed:

  1. before system development begins.
  2. at system development.
  3. at each stage of the system development life cycle (SDLC).
  4. during the development of the business case.

Answer(s): C

Explanation:

Risk assessments are most effective when performed at each stage of the system development life cycle (SDLC). The SDLC is a framework that defines the phases and activities of developing, implementing, and maintaining a system. The SDLC typically consists of the following stages: initiation, planning, analysis, design, development, testing, implementation, and maintenance. Performing risk assessments at each stage of the SDLC helps to identify, analyze, and evaluate the risks that could affect the system objectives, requirements, functionality, quality, or performance. Performing risk assessments at each stage of the SDLC also helps to select and implement the appropriate risk responses, such as avoiding,

transferring, mitigating, or accepting the risks. Performing risk assessments at each stage of the SDLC also helps to monitor and report the risk status and performance, and to update and adjust the risk assessment and response as the system changes or evolves. Performing risk assessments before system development begins, at system development, or during the development of the business case are not as effective as performing risk assessments at each stage of the SDLC, as they are either too early or too late, and they do not capture the full scope and complexity of the system risks. References = CRISC Review Manual, 6th Edition, ISACA, 2015, page 49.



In the three lines of defense model, a PRIMARY objective of the second line is to:

  1. Review and evaluate the risk management program.
  2. Ensure risk and controls are effectively managed.
  3. Implement risk management policies regarding roles and responsibilities.
  4. Act as the owner for any operational risk identified as part of the risk program.

Answer(s): B

Explanation:

The second line of defense provides oversight functions, ensuring that risks and controls are effectively managed. This includes policy enforcement, compliance monitoring, and risk program evaluation, aligning with the organizational risk governance structure as described in the CRISC framework.



Which of the following BEST supports the management of identified risk scenarios?

  1. Collectingrisk event data
  2. Maintaining a risk register
  3. Using key risk indicators (KRIs)
  4. Defining risk parameters

Answer(s): D



Which of the following is the BEST metric to demonstrate the effectiveness of an organization's change management process?

  1. Increase in the frequency of changes
  2. Percent of unauthorized changes
  3. Increase in the number of emergency changes
  4. Average time to complete changes

Answer(s): B

Explanation:

A change management process is a set of procedures and activities that aim to ensure that changes in an organization's IT systems and services are implemented in a controlled and coordinated manner. The effectiveness of a change management process can be measured by how well it reduces the risks and costs associated with changes, and how well it supports the business objectives and customer expectations. One of the best metrics to demonstrate the effectiveness of a change management process is the percent of unauthorized changes. Unauthorized changes are changes that are made without following the established change management process, such as obtaining approval, documenting the change, testing the change, and communicating the change. Unauthorized changes can introduce errors, defects, security breaches, and disruptions to the IT systems and services, and can negatively affect the business performance and customer satisfaction. Therefore, a low percent of unauthorized changes indicates that the change management process is effective in ensuring that changes are properly planned, approved, executed, and monitored. The other options are not the best metrics to demonstrate the effectiveness of a change management process, as they do not directly reflect the quality and control of the changes. An increase in the frequency of changes may indicate that the organization is agile and responsive to the changing business needs and customer demands, but it does not necessarily mean that the changes are well- managed and beneficial. An increase in the number of emergency changes may indicate that the organization is able to handle urgent and critical situations, but it may also suggest that the organization is reactive and lacks proper planning and analysis of the changes. The average time to complete changes may indicate the efficiency and speed of the change management process, but it does not measure the effectiveness and value of the changes. References = CRISC Review Manual, pages 156-1571; CRISC Review Questions, Answers & Explanations Manual, page 712



Mitigating technology risk to acceptable levels should be based PRIMARILY upon:

  1. organizational risk appetite.
  2. business sector best practices.
  3. business process requirements.
  4. availability ofautomated solutions

Answer(s): A

Explanation:

Mitigating technology risk to acceptable levels means that the organization implements and maintains appropriate controls to reduce the likelihood and impact of potential threats or losses that may arise from the use of technology, such as IT systems, applications, networks, devices, etc.
The primary factor that should guide the mitigation of technology risk is the organizational risk appetite. This means that the organization defines and communicates the amount and type of risk that it is willing to accept or pursue in order to achieve its objectives and strategy.
The organizational risk appetite helps to determine the risk tolerance and thresholds for different risk categories and scenarios, prioritize the risks, select the most suitable risk responses, allocate the resources and budget for risk management, and monitor and report the risk performance and outcomes.
The other options are not the primary factors that should guide the mitigation of technology risk. They are either secondary or not essential for risk management.
The references for this answer are:
Risk IT Framework, page 25
Information Technology & Security, page 19
Risk Scenarios Starter Pack, page 17



Viewing page 175 of 380
Viewing questions 871 - 875 out of 1895 questions


Post your Comments and Discuss ISACA CRISC exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!