An organization's business gap analysis reveals the need for a robust IT risk strategy.
Which of the following should be the risk practitioner's PRIMARY consideration when participating in development of the new strategy?

  1. Scale of technology
  2. Risk indicators
  3. Risk culture
  4. Proposed risk budget

Answer(s): C

Explanation:

The risk practitioner's primary consideration when participating in development of a new IT risk strategy should be the risk culture of the organization. Risk culture is the set of values, beliefs, attitudes, and behaviors that shape how the organization perceives, manages, and responds to risks. Risk culture influences the organization's risk appetite, risk objectives, risk policies, risk processes, and risk performance. The risk practitioner should consider the risk culture whendeveloping a new IT risk strategy, because it helps to align the IT risk strategy with the organization's mission, vision, values, and strategy, and to ensure that the IT risk strategy is supported and accepted by the organization's stakeholders, such as the board, management, employees, customers, regulators, etc. The risk practitioner should also consider the risk culture when developing a new IT risk strategy, because it helps to identify and addressany gaps, issues, or challenges that may affect the implementation and effectiveness of the IT risk strategy, such as lack of awareness, communication, coordination, or accountability. The other options are not the primary consideration for the risk practitioner, although they may be related to the IT risk strategy. Scale of technology, risk indicators, and proposed risk budget are all factors that could affect the feasibility and sustainability of the IT risk strategy, but they do not necessarily reflector influence the organization's risk culture. References = Risk and Information Systems Control Study Manual, Chapter 1, Section 1.2.1, page 1-9.



Using key risk indicators (KRIs) to illustrate changes in the risk profile PRIMARILY helps to:

  1. communicate risk trends to stakeholders.
  2. assign ownership of emerging risk scenarios.
  3. highlight noncompliance with the risk policy
  4. identify threats to emerging technologies.

Answer(s): A

Explanation:

The primary purpose of using key risk indicators (KRIs) to illustrate changes in the risk profile is to communicate risk trends to stakeholders. KRIs are metrics that provide an early warning of increasing risk exposure in various areas of the organization. By using KRIs to illustrate changes in the risk profile, the organization can communicate the risk trends to the stakeholders, such as the board, senior management, business units, and external parties, and enable them to take appropriate actions to manage the risk. Assigning ownership of emerging risk scenarios, highlighting noncompliance with the risk policy, and identifying threats to emerging technologies are other possible purposes, but they are not as important as communicating risk trends to stakeholders. References = ISACA Certified in Risk and Information Systems Control(CRISC) Certification Exam Question and Answers, question 12; CRISC Review Manual, 6th Edition, page 215.



Which of the following would provide the MOST helpful input to develop risk scenarios associated with hosting an organization's key IT applications in a cloud environment?

  1. Reviewing the results of independent audits
  2. Performing a site visit to the cloud provider's data center
  3. Performing a due diligence review
  4. Conducting a risk workshop with key stakeholders

Answer(s): D

Explanation:

The most helpful input to develop risk scenarios associated with hosting an organization's key IT applications in a cloud environment is conducting a risk workshop with key stakeholders. A risk workshop is a facilitated session that involves brainstorming, discussing, and analyzing the potential risks and opportunities related to a specific topic or project. A risk workshop helps to identify and prioritize the most relevant and significant risk scenarios, as well as to explore the possible causes, impacts, and responses. A risk workshop also helps to engage and align the key stakeholders, such as the business owners, IT managers, cloud providers, and risk experts, and to leverage their knowledge, experience, and perspectives.

The other options are not as helpful as conducting a risk workshop, although they may provide some inputor information for the risk scenario development. Reviewing the results of independent audits, performing a site visit to the cloud provider's data center, and performing a due diligence review are all activities that can help to assess the current state and performance of the cloud environment, but they do not necessarily generate or evaluate the risk scenarios. References = Risk and Information Systems Control Study Manual, Chapter 4, Section 4.2.1, page 4-13.



An organization's chief information officer (CIO) has proposed investing in a new. untested technology to take advantage of being first to market Senior management has concerns about the success of the project and has set a limit for expenditures before final approval. This conditional approval indicates the organization's risk:

  1. capacity.
  2. appetite.
  3. management capability.
  4. treatment strategy.

Answer(s): B

Explanation:

The conditional approval of the CIO's proposal indicates the organization's risk appetite. Risk appetite is the amount and type of risk that an organization is willing to accept in pursuit of its objectives. By setting a limit for expenditures before final approval, senior management isexpressing their willingness to take a calculated risk with the new technology, but also their desire to control the potential loss or harm. Risk capacity, management capability, and treatment strategy are other possible factors, but they are not as relevant as risk appetite. References = ISACA Certified in Risk and Information Systems Control (CRISC) Certification Exam Question and Answers, question 8; CRISC Review Manual, 6th Edition,

page 97



Which of the following will BEST help to improve an organization's risk culture?

  1. Maintaining a documented risk register
  2. Establishing a risk awareness program
  3. Rewarding employees for reporting security incidents
  4. Allocating resources for risk remediation

Answer(s): B

Explanation:

A risk awareness program is a set of activities that aim to educate and inform employees about the organization's risk culture, policies, and procedures. A risk awareness program can help improve an organization's risk culture by enhancing the employees' understanding of risk, their roles and responsibilities in risk management, and the benefits of risk mitigation. A risk awareness program can also foster a culture of openness, trust, and collaboration among employees, managers, and stakeholders, which can improve the organization's risk performance and resilience.
Maintaining a documented risk register, rewarding employees for reporting security incidents, and allocating resources for risk remediation are also important aspects of risk management, but they do not directly address the organization's risk culture, which is the shared values, beliefs, and attitudes that influence how risk is perceived and handled within the organization.