You are the program manager for your project. You are working with the project managers regarding the procurement processes for their projects. You have ruled out one particular contract type because it is considered too risky for the program.
Which one of the following contract types is usually considered to be the most dangerous for the buyer?

  1. Cost plus incentive fee
  2. Time and materials
  3. Cost plus percentage of costs
  4. Fixed fee

Answer(s): C



Which of the following NIST documents provides a guideline for identifying an information system as a National Security System?

  1. NIST SP 800-53
  2. NIST SP 800-59
  3. NIST SP 800-53A
  4. NIST SP 800-37
  5. NIST SP 800-60

Answer(s): B



You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you will need eleven inputs for the process.
Which one of the following is NOT an input to the risk identification process?

  1. Cost management plan
  2. Procurement management plan
  3. Stakeholder register
  4. Quality management plan

Answer(s): B



There are seven risks responses that a project manager can choose from.
Which risk response is appropriate for both positive and negative risk events?

  1. Acceptance
  2. Mitigation
  3. Sharing
  4. Transference

Answer(s): A