What course of action can be taken by a party if the current negotiations fail and an agreement cannot be reached?

  1. PON
  2. ZOPA
  3. BATNA
  4. Bias

Answer(s): C



Which of the following is the acronym of RTM?

  1. Resource tracking method
  2. Requirements Traceability Matrix
  3. Resource timing method
  4. Requirements Testing Matrix

Answer(s): B



Thomas is the project manager of the NHJ Project for his company. He has identified several positive risk events within his project and he thinks these events can save the project time and money. Positive risk events, such as these within the NHJ Project are also known as what?

  1. Opportunities
  2. Benefits
  3. Ancillary constituent components
  4. Contingency risks

Answer(s): A



You are the project manager of the GGG project. You have completed the risk identification process for the initial phases of your project. As you begin to document the risk events in the risk register what additional information can you associate with the identified risk events?

  1. Risk schedule
  2. Risk potential responses
  3. Risk cost
  4. Risk owner

Answer(s): B