Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. (for 2 out of 3 correct )

  1. Test planning, test case preparation and test execution for each of the four iterations
  2. Work should be explicitly allocated to test completion, test management, installation and to training on using the system
  3. Activities to deploy the system in the user environment
  4. Regression testing in the second, third and fourth iterations
  5. Development activities for unit and integration testing
  6. Reviews on requirements documentation
  7. Defining test environment requirements for system testing

Answer(s): A,B,D



View Related Case Study

In general which part of the testing activity is most difficult to estimate?

  1. Test planning
  2. Test execution
  3. Test management
  4. Test design

Answer(s): B



View Related Case Study

In general, why is it NOT a good idea to estimate the testing effort based only on a percentage of development effort? Identify THREE valid reasons.

  1. The quality of the development estimate may be poor.
  2. In general bottom-up estimation is always better than top-down estimation.
  3. The percentage based technique only applies to the V life cycle model.
  4. Using the same percentage every time does not address the level of risk of the application to be tested.
  5. The maturity of the organization, e.g. the quality of the test basis, quality of development testing, configuration management, availability of test tools, also influence the effort needed for testing.
  6. It builds on large set of historical data
  7. The result is almost always a too low estimate for the required test effort

Answer(s): A,D,E



View Related Case Study

Which aspect in the test estimate is the main risk in this project?

  1. Quality of the specification
  2. Availability of end-users
  3. The costs of hardware and tools
  4. Unknown input quality due to third party development

Answer(s): D