Free CTFL-FOUNDATION Exam Braindumps (page: 14)

Page 13 of 85

Which of the following phases in the fundamental test process is considered to deliver a document which can be used as a major input for test process improvement?

  1. Test planning and control
  2. Test implementation & execution
  3. Evaluating exit criteria and reporting
  4. Test project closure

Answer(s): D



Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

a). Any deviation from the procedures described in the test
b). strategy document
c). The overall estimated costs, timescales and resource
d). requirements
e). A detailed schedule of testing activities
f). The development deliverables to be tested
g). Which test staff members (names) will be involved and when
h). Level of requirements coverage achieved

Which TWO of the above mentioned characteristics relate to the phase test plan?

  1. a
  2. b
  3. c
  4. d
  5. e
  6. f

Answer(s): C,E



Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

a). Any deviation from the procedures described in the test strategy document
b). The overall estimated costs, timescales and resource requirements
c). A detailed schedule of testing activities
d). The development deliverables to be tested
e). Which test staff members (names) will be involved and when
f). Level of requirements coverage achieved

Which THREE of the above mentioned characteristics relate to the master test plan?

  1. a
  2. b
  3. c
  4. d
  5. e
  6. f

Answer(s): A,B,D



Which THREE activities would be valid steps during the development of the test strategy? (2 out of 3 correct )

  1. Identify test staff members that will be involved in the system test
  2. Define test career paths
  3. Understand the software development life cycle used by the software house
  4. Assess the testing that needs to be done to minimize the risks
  5. Issue the test strategy document for review
  6. Define a master test plan template
  7. Perform a project risk analysis

Answer(s): C,D,E






Post your Comments and Discuss ISTQB® CTFL-FOUNDATION exam with other Community members:

CTFL-FOUNDATION Discussions & Posts