Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status?

  1. Criteria A = OK, criteria B = OK, criteria C = OK
  2. Criteria A = NOT OK, criteria B = NOT OK, criteria C = OK
  3. Criteria A = OK, criteria B = NOT OK, criteria C = NOT OK
  4. Criteria A = NOT OK, criteria B = NOT OK, criteria C = NOT OK

Answer(s): B



View Related Case Study

You have investigated different possibilities and selected four of them to present to IT management. Which of the proposals will you most likely give your highest recommendations?

  1. Insourcing of test automation based on an offer from a local company ABC that has people who are specialists in system level capture-replay automation tools and they also do regular training courses in test automation methods and tools. They can then work closely with Vicki.
  2. Outsourcing of test automation based on an offer from an Asian company, AsiaAutoTest, which has people who are specialists in system level capture-replay automation tools. They also offer training and besides they offer to run and maintain the regression tests in the future.
  3. Internal offer from the development department of XYZ to create the regression package using CppUnit as test automation tool. One of the development groups have very good experiences in automating unit tests, and they are willing to do training as well.
  4. Solution from a tool vendor offering to educate two test team members in the use of their easy-to-use test automation capture replay tool over the first 3 month and based on that build the regression test suite. In addition to Vicki, Steve is the only one that has time available to be educated.

Answer(s): A



View Related Case Study

Instead of having an independent test team within the company, the company is considering to outsource testing. What are THREE key challenges that are typical for outsourcing?

  1. Test environment more complex
  2. Define expectation for tasks and deliverables
  3. Clear channels of communications
  4. Possibly different cultures
  5. Testing of non-functional requirements
  6. Audit trail from requirements to test cases
  7. Applying test automation

Answer(s): B,C,D



View Related Case Study

Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. (for 2 out of 3 correct )

  1. Test planning, test case preparation and test execution for each of the four iterations
  2. Work should be explicitly allocated to test completion, test management, installation and to training on using the system
  3. Activities to deploy the system in the user environment
  4. Regression testing in the second, third and fourth iterations
  5. Development activities for unit and integration testing
  6. Reviews on requirements documentation
  7. Defining test environment requirements for system testing

Answer(s): A,B,D