As part of the test strategy, entry and exit criteria will be defined for each test level. Which is NOT a valid reason for using entry and exit criteria?

  1. The expectation is that development testing is not adequate.
  2. Exit criteria are used to decide on when to stop testing.
  3. Entry and exit criteria are a principal way for getting adequate resources.
  4. Using entry and exit criteria will prevent software that is not or poorly tested from going to the next test level.

Answer(s): C



View Related Case Study

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

a). Any deviation from the procedures described in the test strategy document
b). The overall estimated costs, timescales and resource requirements
c). A detailed schedule of testing activities
d). The development deliverables to be tested
e). Which test staff members (names) will be involved and when
f). Level of requirements coverage achieved

Which THREE of the above mentioned characteristics relate to the master test plan?

  1. a
  2. b
  3. c
  4. d
  5. e
  6. f

Answer(s): A,B,D



View Related Case Study

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

a). Any deviation from the procedures described in the test
b). strategy document
c). The overall estimated costs, timescales and resource
d). requirements
e). A detailed schedule of testing activities
f). The development deliverables to be tested
g). Which test staff members (names) will be involved and when
h). Level of requirements coverage achieved

Which TWO of the above mentioned characteristics relate to the phase test plan?

  1. a
  2. b
  3. c
  4. d
  5. e
  6. f

Answer(s): C,E



View Related Case Study

Which of the following product risks would be most effectively addressed just by static testing?

  1. In the delivered application, one of the countries, as specified in the requirements, has not been correctly implemented.
  2. The application takes too long to process a request for additional cover.
  3. The test cases do not cover the key requirements.
  4. The successful bidder may not deliver all the required functionality on time.

Answer(s): C



View Related Case Study

The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses. Which of the following checkpoints would be appropriate?

  1. The bidder's test policy should enforce that incident management fully conforms to IEEE 1044.
  2. The bidder's project strategy shows that the data content of all the test environments conforms to EU standards.
  3. The bidder's test plan shows that the application will be delivered for acceptance in six months time.
  4. The bidder's project test plan depicts a phased implementation with later delivery dates to be confirmed and states that test deliverables will be developed using IEEE 829 as a guide.

Answer(s): D