Lessons learned are most often based upon project historical records. Lessons learned can be used to:

  1. See how others have solved problems
  2. "Predict trends, highlight problems and identify alternatives"
  3. See what mistakes others have made
  4. All of the other alternatives apply

Answer(s): D



In which type of organization(s) is the project manager's role most likely part-time?

  1. Functional
  2. Weak Matrix
  3. Balanced Matrix
  4. Both 1) Functional and 2) Weak Matrix

Answer(s): D



A(n) _____ is defined as a specified accomplishment in a particular instant in time which does not consume time or resources.

  1. Event.
  2. Activity
  3. Correlation
  4. Event constrained within planned effort.
  5. Constant

Answer(s): A



Trend Analysis is best described as:

  1. Examining project performance over time
  2. Calculating Earned Value
  3. Calculating Cost Variance
  4. Analyzing performance of similar projects over time

Answer(s): A



Overlapping activities on a project, such as design and construction, is referred to as:

  1. Process improvement.
  2. Synchronous manufacturing
  3. Fast tracking
  4. Parallel management.
  5. Risk conversion.

Answer(s): C