Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

  1. 6.1
  2. 6.3
  3. 6
  4. 4

Answer(s): C



Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.

  1. Increase, increase.
  2. Increase, decrease.
  3. Remain the same, return to customer.
  4. Decrease, increase.
  5. Decrease, decrease.

Answer(s): C



The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form does the project manager probably have the easiest time in integrating work?

  1. Matrix
  2. Pure project
  3. Coordinator
  4. Classical
  5. Expediter

Answer(s): B



Formal written correspondence is mandated in which of the following situations:

  1. Client requests additional work not covered under contract
  2. None of the other alternatives apply
  3. Both 1) Client requests additional work not covered under contract, and 2) Project manager calls a meeting.
  4. Project manager calls a meeting
  5. Product undergoes casual in-house testing

Answer(s): A