All of the following may hinder a person's ability to transmit/receive a message except:

  1. Preoccupation
  2. Assuming
  3. Unfamiliarity with topic
  4. Noise
  5. Withholding information

Answer(s): C



The Communications Management Plan should contain the following:

  1. Selection of appropriate media to meet specific needs
  2. Communications policy
  3. All of the other alternatives apply
  4. Communications media
  5. Reporting channels

Answer(s): C



A project manager believes that the best way to manage is to form a good, harmonious working relationship with the team, and high performance will follow. The project manager could be defined as a _____ manager.

  1. 1,9
  2. 9,1
  3. 1,1
  4. 9,9
  5. 5,5

Answer(s): A



Which involves estimating the cost of individual work items:

  1. Analogous estimating
  2. Bottom up estimating
  3. Computerized
  4. Square foot

Answer(s): B



You are a project manager for the Swirling Seas Cruises food division. You're considering two different projects regarding food services on the cruise lines. The initial cost of Project Fish'n for Chips will be $800,000, with expected cash inflows of $300,000 per quarter. Project Picnic's payback period is six months.
Which project should you recommend?

  1. Project Fish'n for Chips, because the costs on Project Picnic are unknown.
  2. Project Picnic, because Project Fish'n for Chips' payback period is two months longer than Project Picnic's.
  3. Project Picnic, because Project Fish'n for Chips' payback period is four months longer than Project Picnic's.
  4. Project Fish'n for Chips, because its payback period is two months shorter than Project Picnic's.

Answer(s): B