Which of the following must not performed in the project initiation process?

  1. Evaluate historical information
  2. List down business need
  3. List down stakeholders
  4. Create scope statement

Answer(s): D



You have assembled your thoughts into a message. As you pass this information to a second party, you are giving this person you're:

  1. Input and Data
  2. Feedback
  3. Data
  4. Output
  5. Input

Answer(s): D



The quality management plan documents how the project team will implement the quality policy.
It must address all of the following except which one?

  1. Continuous process improvement
  2. Quality assurance
  3. Quality control
  4. Quality checklists

Answer(s): D



Which quality management tool would be used to determine potential causes of a production problem?

  1. run chart.
  2. scatter diagram.
  3. histogram.
  4. control chart.
  5. Ishikawa diagram.

Answer(s): E



A project may be defined as ________.

  1. an integrated approach to managing projects
  2. a coordinated undertaking of interrelated activities.
  3. a group of activities directed by a project manager over a life cycle
  4. All of the other alternatives apply.
  5. an undertaking with a defined starting point and defined objectives

Answer(s): E