If you know expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following?
Answer(s): C
You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the project scope.Which of the following statements is true?
Answer(s): A
You are managing an internal project where a vice president from the user group is acting as the sponsor. You have just been informed by your team that the critical path has slipped by three weeks.You should:
Parametric estimates are based on variables such as:
Answer(s): B
All of the following are true regarding Communications Planning except for which one?
Post your Comments and Discuss ITIL ISEB-PM1 exam prep with other Community members:
Our website is free, but we have to fight against AI bots and content theft. We're sorry for the inconvenience caused by these security measures. You can access the rest of the ISEB-PM1 content, but please register or login to continue.