ISEB-PM1 Foundation Certificate in Project Management Questions 316–320 (page: 65)

Updated On: 10-Feb-2026

How is quality control performed?

  1. By identifying quality standards that are relevant to the project and determining how to satisfy them.
  2. By monitoring specific project results in compliance with relevant quality standards and determining corrective actions as needed.
  3. By ensuring that the entire project team has been adequately trained in quality assurance processes.
  4. By applying Monte Carlo, sampling, Pareto analysis and benchmarking techniques to ensure conformance to quality standards.

Answer(s): B



As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost.
You should calculate the forecast using which of the following methods?

  1. BAC
  2. EAC
  3. ETC
  4. WBS

Answer(s): B



How is scheduled variance calculated using the earned value technique?

  1. EV less AC
  2. AC less PV
  3. EV less PV
  4. AC less EV

Answer(s): C



The project management processes presented in the PMBOK Guide should:

  1. Always be applied uniformly
  2. Be selected as appropriate by the sponsor
  3. Be selected as appropriate by the project team
  4. Be applied based on ISO guidelines.

Answer(s): C



Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?

  1. Project sponsor and project manager
  2. Project sponsor and functional manager
  3. Project manager and project team
  4. Project team and functional manager

Answer(s): C