Which of the following methods is a project selection technique?

  1. Flowcharting
  2. Earned value
  3. Cost-benefit analysis
  4. Pareto analysis

Answer(s): C



While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery.
What is the MOST appropriate approach to managing this situation?

  1. Utilize the change control process.
  2. Crash the schedule to fix the defect.
  3. Leave the defect in and work around it.
  4. Fast-track the remaining development.

Answer(s): A



Which tool is used to develop technical details within the project management plan?

  1. Expert Judgment
  2. Project Management Methodology
  3. Project Management Information
  4. Project Selection Methods

Answer(s): A



Which of the following are outputs of the Monitor and Control Project Work process?

  1. Requested changes, forecasts, recommended corrective actions
  2. Forecasts, resources plan, bottom up estimating
  3. Recommended corrective actions, cost baseline, forecasts
  4. Requested changes, recommended corrective actions, project constraints

Answer(s): A



Which tool or technique measures performance of the project as it moves from project initiation through project closure?

  1. Resource leveling
  2. Parametric measuring
  3. Pareto chart
  4. Earned value

Answer(s): D