What can a risk-based approach to testing provide?

  1. The types of test techniques to be employed.
  2. The total tests needed to provide 100 per cent coverage.
  3. An estimation of the total cost of testing.
  4. Only that test execution is effective at reducing risk.

Answer(s): A



View Related Case Study

When assembling a test team to work on an enhancement to an existing system, which of the following has the highest level of test independence?

  1. A business analyst who wrote the original requirements for the system.
  2. A permanent programmer who reviewed some of the new code, but has not written any of it.
  3. A permanent tester who found most defects in the original system.
  4. A contract tester who has never worked for the organization before.

Answer(s): D

Explanation:

In this scenario, the contract tester who has never worked for the organization before has the highest level of test independence. The three others are less independent as they are likely to make assumptions based on their previous knowledge of the requirements, code and general functionality of the original system.
Note that independence does not necessarily equate to most useful. In practice most test or project managers would recruit a permanent tester who has worked on the original system in preference to a contract tester with no knowledge of the system. However, when assembling a team it would be useful to have staff with varying levels of test independence and system knowledge.



View Related Case Study

Which of the following terms is used to describe the management of software components comprising an integrated system?

  1. Configuration management
  2. Incident management
  3. Test monitoring
  4. Risk management

Answer(s): A

Explanation:

Incident management is the collection and processing of incidents raised when errors and defects are discovered. Test monitoring identifies the status of the testing activity on a continuous basis. Risk management identifies, analyses and mitigates risks to the project and the product. Configuration management is concerned with the management of changes to software components and their associated documentation and testware.



View Related Case Study

A new system is about to be developed.
Which of the following functions has the highest level of risk?

  1. Likelihood of failure = 20%; impact value = £100,000
  2. Likelihood of failure = 10%; impact value = £150,000
  3. Likelihood of failure = 1%; impact value = £500,000
  4. Likelihood of failure = 2%; impact value = £200,000

Answer(s): A

Explanation:

In (B) the product of probability × impact has the value £15,000; in (C) the value is £5,000 and in (D) it is £4,000. The value of £20,000 in (A) is therefore the highest.



View Related Case Study

Which of the following statements about risks is most accurate?

  1. Project risks rarely affect product risk.
  2. Product risks rarely affect project risk.
  3. A risk-based approach is more likely to be used to mitigate product rather than project risks.
  4. A risk-based approach is more likely to be used to mitigate project rather than product risks.

Answer(s): C

Explanation:

In general, project risk and product risk can be hard to differentiate. Anything that impacts on the quality of the delivered system is likely to lead to delays or increased costs as the problem is tackled. Anything causing delays to the project is likely to threaten the delivered system's quality. The risk- based approach is an approach to managing product risk through testing, so it impacts most directly on product risk.



Viewing page 20 of 69