QUESTION: 1
Your organization uses Project Professional 2013 and records actual hours worked on the
project. You manage a small e-commerce website implementation project. One of your testers
asks for assistance in completing a critical task, and you find two additional testing resources
that can assist with executing the critical test cases. The total estimated work for the effort-
driven task is 100 hours. The original testing resource, Resource1, completes 25 hours of work
on the task. You need to add Resource2 and Resource3 to the task and split the remaining
hours across all three resources now working on the task. Which two actions should you
perform? (Each correct answer presents part of the solution. Choose two.)
A. Open the Task Form and format it to show Work Details. Enter 25 hours of actual work for
Resource1. Then save the changes.
B. Open the Task Form and format it to show Work Details. Enter 75 hours of remaining work
for the assigned resource. Then save the changes.
C. Assign Resource2 and Resource3 to the task. Then save the changes.
D. Open the Task Form and format it to show Work Details. Enter 33.33 hours of work for each
resource. Then save the changes.
Answer(s): A, C
QUESTION: 2
You are managing a project using Project Professional 2013. Your project schedule is showing
task overallocation indicators in the Gantt chart view. You navigate to the Team Planner view to
investigate more details regarding the over allocations. You discover that the BA1 resource is
overallocated and you need to see all assignments with details for BA1 to understand their
current workload before making any assignment changes. What should you do?
A. Click the BA1 resource and scroll to the end of the project.
B. Click View, check Details, select Resource Form then click on the BA1 resource.
C. Click View, check Details, select Task Form then click on the BA1 resource.
D. Right-click the BA1 resource and select Information.
Answer(s): B
QUESTION: 3
You are a project manager who uses Project Standard 2013. You are creating a preliminary
project schedule and are estimating the number of resources required prior to finalizing the
schedule. You do not have named resources to complete the tasks, but you know the resource
roles that are necessary. One of the roles needed is architect. You need to estimate how many
architect hours are required to complete the work. What should you do?
A. Add a Material Resource named architect.
B. Add a Budget Resource named architect.
C. Add a Work Resource named architect,
D. Add a Cost Resource named architect.
Answer(s): C