HOTSPOT

A company produces homeopathic lotions for pain relief and uses Dynamics 365 Supply Chain Management.

Several components used in the production of the pain-relieving lotion and oils have special government- mandated reporting requirements.

You need to ensure the company can provide the appropriate reporting and tracking for these components.

Which parameters should you use? To answer, select the appropriate options in the answer area.

Note: Each correct selection is worth one point.

Hot Area:

  1. See Explanation section for answer.

Answer(s): A


Reference:

https://community.dynamics.com/365/supply-chain-management/b/
axsupplychainmanagementandmanufacturing/posts/managing-compliance-with-process-manufacturing-in- dynamics-ax2012
https://docs.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/set-up-product-compliance-parameters



You are the lead product design engineer at a plastics manufacturing company.

You implement a new process that uses a single tool to produce three finished goods at the same time.

You need to set up the planning item number and formula to correctly to manufacture the three items.

Which three actions should you perform? Each correct answer presents part of the solution.

Note: Each correct selection is worth one point.

  1. Create item number for planning item and the associated formula.
  2. Specify each of the finished good items as co-products.
  3. Add minimum and maximum quantities on formula.
  4. Assign co-products to the formula.
  5. Add a coverage group to the formula.

Answer(s): A,B,D



A company produces multiple products that require an installation kit that includes 50 components.

The company does not want to include these 50 components in every Bill of materials (BOM). You have a BOM kit that includes all 50 components, but you do not want it to produce a separate production order.

You need to set up the product BOM for the finished good.

What should you do?

  1. Change the coverage group on the kit item to Manual.
  2. Select Phantom on the engineering fast tab on the kit item.
  3. Change the line type to Pegged supply.
  4. Change the line type to Phantom.

Answer(s): D



A company produces rubber hose. Discrete orders accounts for raw material scrap. The scrap is reported through inventory movement journals.

The company has noticed that most of the scrap that is recorded is due to start up that feeds the hose to the finishing process. In addition, the amount of scrap that is recorded is consistent regardless of the amount of hose being produced.

You need to account for material lost during startup.

What should you do?

  1. Enter the consumption amount on the line to match the actual amount used.
  2. Do a case study for the scrap items and enter the average amount of scrap as separate line items on the Bill of materials.
  3. Enter the amount of scrap that is consumed as constant scrap in the Bill of materials.
  4. Enter the amount of scrap that is consumed as variable scrap in the Bill of materials.

Answer(s): C



A manufacturer uses Dynamics 365 Supply Chain Management.

The engineering department constantly revises product designs to stay current with the latest technology. The customer service department places orders for the products but frequently adds a prototype product version that is not yet operational.

The manufacturer requires a solution that notifies customer service if a prototype version is selected on a sales order.

You need to configure the solution.

What should you configure?

  1. product release policy
  2. product lifecycle states
  3. version number rule
  4. engineering product category

Answer(s): D

Explanation:

Engineering versions and engineering product categories
Engineering products evolve during their product lifecycle, for many reasons. For example, changes might be introduced to improve product serviceability, change a component because the supplier no longer offers it, respond to new insights, or fix mistakes in the initial design. There are also many reasons why these changes should be stored as part of an ongoing product, in such a way that previous data isn't overwritten. Here are some of these reasons:
You want to keep track of the product as it was manufactured and delivered to your customers in previous lifecycle states.

You need a lead time before you approve and apply the changes.
You want to have a timestamp on each change, and you want to be able to deliver previously manufactured products separately from each other.
Engineering versions ensure that the various states of a product and its data are kept current and clear, and that they can be visualized in the system. This concept helps you maintain consistency, lock down the bill of materials (BOM) for production, eliminate variability, and easily identify changes.


Reference:

https://learn.microsoft.com/en-us/dynamics365/supply-chain/engineering-change-management/engineering- versions-product-category



Viewing page 10 of 55
Viewing questions 46 - 50 out of 270 questions