DRAG DROP (Drag and Drop is not supported)
A large company is enrolled in the Dynamics 365 Supply Chain Management FastTrack program.
A user wants to know when the data sources for reporting and required reports will be designeD.
You need to identify the Success by Design stage that will address the report and data questions.
In which stage will each activity occur? To answer, drag the appropriate stages to the correct requirements. Each stage may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.

- See Explanation section for answer.
Answer(s): A
Explanation:

Box 1: Implement
Design reports
In the Implement phase, the project team is focused on building the solution per the agreed upon solution design and scope. This phases introduces Implementation Reviews that come from the findings and recommendations of the Solution Blueprint Review. As we learn in the section Success by Design reviews section, Implementation Reviews help you more deeply address questions related to the specific aspects of the solution design (data model, security, and integration) and implementation practices (ALM, testing strategy). Implementation Reviews are meant to fully address the risks identified during or after the Solution Blueprint Review but before the solution build is too far along.
Box 2: Initiate
Identify report data source
In the Initiate phase, the project team is in discovery mode, gathering and validating business requirements, finalizing the high-level solution approach, making inroads to define all in-scope workstreams, and updating the project plan to reflect these updates. When the project team has produced the high-level solution design and the related project workstreams are more or less defined, Success by Design begins with the Solution Blueprint Review.
Note: The figure below illustrates that Success by Design reviews aren't to be conducted as abstract exercises separated from the project. Rather, the scheduling and implementation of each review relies on the availability of key project artifacts and the readiness of the project team to discuss them.

Reference:
https://learn.microsoft.com/en-us/dynamics365/guidance/implementation-guide/success-by-design