DRAG DROP (Drag and Drop is not supported)
A company plans to implement Dynamics 365 Supply Chain Management.
The company’s employees have been using the same system and processes for many years. Employees are reluctant to change the old processes.
You need to create an adoption plan and measure the effectiveness of the plan.
In which phase does each activity belong? To answer, drag the appropriate phases to the correct activities. Each phase may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
- See Explanation section for answer.
Answer(s): A
Explanation:
Box 1: Onboard
Phase two: Onboard
Work with your key stakeholders to build and launch your adoption plan. Prepare your environment and test your adoption approach with Early Adopters. Use feedback to make adjustments before scaling to the business. In this phase, you will:
•Build your adoption plan.
•Launch to Early Adopters.
•Adjust your plan.
Box 2: Drive value
Phase three: Drive value
Full-scale deployment and business success depend on usage and satisfaction. This requires planning through the Envision and Onboard phases plus ongoing operational excellence. In this phase, you will:
•Monitor end-user adoption.
•Measure and report usage.
•Encourage ongoing engagement.
Incorrect:
Envision
In the first phase of the Adoption Framework, you identify and prioritize scenarios while learning about available resources as you plan for rollout. This stage is critical to your journey because you're setting business goals to measure success.
The key steps in the Envision phase are:
•Assemble your team
•Define business strategy
•Determine readiness
Reference: