Free PDM_2002001060 Exam Braindumps (page: 26)

Page 25 of 54

Which of the following statements is correct?

  1. An accuracy KPI that increases and a deviation KPI that increases shows that your project is under control.
  2. An accuracy KPI that decreases and a deviation KPI that increases shows that your project is under control.
  3. An accuracy KPI that decreases and a deviation KPI that decreases shows that your project is under control.
  4. An accuracy KPI that increases and a deviation KPI that decreases shows that your project is under control.

Answer(s): D



What are the basic elements for estimate at completion reporting?

  1. Detailed plan - actual costs.
  2. CBL - ETC .
  3. ASCE + ET
  4. Actual Costs + ETC.

Answer(s): D



The EVM measure which best shows the difference between budgeted cost and actual cost is:

  1. cost variance.
  2. percentage over or under.
  3. SPI.
  4. this is not a valid measure.

Answer(s): A



What is the relationship between a Business Case and a Project?

  1. A business case and a project will always have a one-to-one relationship.
  2. A business case can contain a number of CAPEX and OPEX projects.
  3. A project can contain a number of business cases.
  4. A business case can contain a number of CAPEX projects but not OPEX projects.

Answer(s): B






Post your Comments and Discuss Nokia PDM_2002001060 exam with other Community members:

PDM_2002001060 Discussions & Posts