QUESTION: 1
You are a portfolio manager, and a filter has been set to identity and assign projects to your
portfolio. You are in Primavera P6 EPPM web interface.
How could you be certain that the list of projects in your portfolio is complete?
A. By manual y hiding projects
B. By manual y adding new projects
C. By manual y refreshing the filter
D. By manual y updating projects
Answer(s): C
Explanation:
The result of filter can be refreshed to ensure that the most current information is displayed.
QUESTION: 2
A Physical % complete activity has an original duration of 10, and a remaining duration of
10. The actual start is assigned to the activity. Physical % is updated to equal 80%. What is
the remaining duration for this activity?
A. 80
B. 10
C. 2
D. 8
Answer(s): B
QUESTION: 3
Select two true statements about the Portfolio Analysis tab in Primavera P6 EPPM.
A. Conducts a side-by-side comparison of an unlimited number of portfolios
B. Conducts a side-by-side comparison of two projects
C. Conducts a side-by-side comparison of two portfolios
D. Conducts a side by-side comparison of one project displayed in different views
E. Conducts a side by-side comparison of the same portfolio displayed in different views
Answer(s): C, E
Explanation:
Note: Creating Projects on the Portfolio Analysis Page
Generally, you create projects while working on the EPS page in the Projects section of the
application. However, it is also possible to create what-if projects while analyzing portfolios.
During the process of evaluating a portfolio, you wil often want to capture a new project
idea. To create a project on the portfolio analysis page:
1) Click Portfolios.
2) On the Portfolios navigation bar, click Portfolio Analysis.
3) On the Portfolio Analysis page:
a. Make sure you are working with the primary portfolio (at top or left) and not the
comparison setfor the next steps.