Free MOR Exam Braindumps (page: 16)

Page 16 of 36

Identify the missing word(s) in the following sentence. The risk [ ? ] used during the 'implement' step compares the performance of response actions with their planned outcomes.

  1. register
  2. management strategy
  3. progress report
  4. response plan

Answer(s): C



What is represented graphically on a 'summary risk profile'?

  1. Proximity of the identified risks
  2. Information found in the risk register
  3. Summary of the actions required to respond to the risks in the activity
  4. Risk capacity for the activity

Answer(s): B



Which is a definition of a risk maturity model?

  1. A framework of mature practices for appraising an organization's risk management competency
  2. A tool for checking the health of current risk management
  3. An assessment of an organization's risk management practice
  4. A self-assessment check that the principles have been applied well

Answer(s): A



Which is a method for obtaining senior management commitment and support for understanding and managing risk?

  1. Developing management of risk guidance handbooks and training materials
  2. Ensuring the risk management function has a direct reporting line to a senior executive
  3. Escalating risks from the programme, project or operational perspectives to higher levels as required
  4. Making formal assessments of management of risk implementation in areas of concern

Answer(s): B



Page 16 of 36



Post your Comments and Discuss PEOPLECERT MOR exam with other Community members: