Which activity is focused on when the 'aligns with objectives' principle is applied to the project perspective?

  1. Delivering a defined business change product within budget
  2. Maintaining the appropriate level of business services to customers
  3. Enhancing an existing capability to improve organizational performance
  4. Ensuring the on-going viability of the organization

Answer(s): A



What is the lack of senior management support a common barrier to?

  1. Identifying key performance indicators
  2. Developing a risk communications plan
  3. Implementing the steps in the risk management process
  4. Involving stakeholders in risk identification

Answer(s): C



What principle promotes dialogue with affected parties in a timely manner to help achieve organizational objectives?

  1. Achieves measurable value
  2. Aligns with objectives
  3. Engages stakeholders
  4. Fits the context

Answer(s): C



What are the M_o_R principles informed by?

  1. Corporate governance principles
  2. Statement of internal control
  3. M_o_R approach
  4. Basel II

Answer(s): A



Page 18 of 36



Post your Comments and Discuss PEOPLECERT MOR exam with other Community members:

Tam commented on April 27, 2024
Very nice mock exam
UNITED KINGDOM
upvote

SavvySurfer commented on June 14, 2022
These notes are very helpful in passing the exam.
UNITED STATES
upvote