Which BEST describes an area of uncertainty at the programme perspective?

  1. Disruptions to operations during business change implementation
  2. Introduction of new laws that affect core business activities
  3. Availability of resources for the day-to-day delivery of services to customers
  4. Changes to the scope of defined business products

Answer(s): A



Which heading in a 'risk register is used to record the area of uncertainty?

  1. Cause
  2. Event
  3. Effect
  4. Probability

Answer(s): B



Which perspective ensures risk management maintains a view of the adequacy of controls that support service delivery to satisfy the fits the context principle?

  1. Strategic
  2. Programme
  3. Operational
  4. Project

Answer(s): C



Which BEST describes an area of uncertainty at the programme perspective?

  1. Schedule of business products to time and cost
  2. Availability of skills to deliver services to new and existing customers
  3. Implementing new business practices across organizational boundaries
  4. Legislation that affects core business activities

Answer(s): C



Which is a common barrier to implementing the risk management process?

  1. Lack of a high-risk appetite at senior management level
  2. Lack of an appropriate response to a risk in an activity's risk register
  3. Lack of an assigned risk owner
  4. Lack of policies, processes, strategies and plans

Answer(s): D