Free CAPM Exam Braindumps (page: 10)

Page 10 of 276

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

  1. Project team
  2. Focus group
  3. Change control board
  4. Project stakeholders

Answer(s): C

Explanation:

Change Control Board (CCB). A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.



Plan Schedule Management is a process in which Knowledge Area?

  1. Project Scope Management
  2. Project Human Resource Management
  3. Project Integration Management
  4. Project Time Management

Answer(s): D

Explanation:

Schedule -> Time Management Easy question



An output of the Validate Scope process is:

  1. A requirements traceability matrix.
  2. The scope management plan.
  3. Work performance reports.
  4. Change requests.

Answer(s): D

Explanation:

Process: 5.5 Validate Scope
Definition: The process of formalizing acceptance of the completed project deliverables.
Key Benefit: The key benefit of this process is that it brings objectivity to the acceptance process and increases the chance of final product, service, or result acceptance by validating each deliverable.

Inputs
1. Project management plan
2. Requirements documentation
3. Requirements traceability matrix
4. Verified deliverables
5. Work performance data

Tools & Techniques
1. Inspection
2. Group decision-making techniques

Outputs
1. Accepted deliverables
2. Change requests
3. Work performance information
4. Project documents updates



The Perform Integrated Change Control process occurs in which Process Group?

  1. Initiating
  2. Executing
  3. Monitoring and Controlling
  4. Planning

Answer(s): C

Explanation:

Monitoring and Controlling Process Group
4.4 Monitor and Control Project Work
4.5 Perform Integrated Change Control
5.5 Validate Scope
5.6Control Scope
6.7 Control Schedule
7.4 Control Costs
8.3 Control Quality
10.3 Control Communications
11.6 Control Risks
12.3 Control Procurements
13.4 Control Stakeholder Engagement



Page 10 of 276



Post your Comments and Discuss PMI CAPM exam with other Community members:

Zee commented on September 21, 2024
Are these useful for CAPM exam in 2024?
SOUTH AFRICA
upvote

DonPook commented on August 18, 2024
Is there any difference in downloading the PDF (paying), to the questions provided for free?
Anonymous
upvote

Sharon commented on August 17, 2024
Which exam questions pack can one use inpreparation for the CAPM exam?
Anonymous
upvote

Priyo commented on November 14, 2023
i used this site since 2000, still great to support my career
INDONESIA
upvote

Priyo commented on November 14, 2023
I used this site since 2000, still great to support my career
INDONESIA
upvote

Shayan commented on June 19, 2023
I am here to let you know that about 4 or 5 new questions are added to this exam. I took the exam today and saw those new questions which are not in your exam dumps. I still passed and got 91%.
UNITED STATES
upvote

Roberto commented on May 04, 2021
This is a good hack to pass the exam.
ITALY
upvote

LarBear commented on January 25, 2019
I have used brain dumps before and working great.
UNITED STATES
upvote

Adrian commented on August 11, 2018
The test engine is for windows only so does not work on my mac (I knew this before purchasing as they mention this on the website). The Android app crashes when I try to activate. I purchased from here because of the apps since I can get the pdf questions from several places on the web. Disappointed customer. Try somewhere else.
UNITED STATES
upvote

Life commented on June 22, 2018
Good CAPM questions AND GUIDE!
UNITED STATES
upvote