Free CAPM Exam Braindumps (page: 11)

Page 10 of 276

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

  1. Project team
  2. Focus group
  3. Change control board
  4. Project stakeholders

Answer(s): C

Explanation:

Change Control Board (CCB). A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.



Plan Schedule Management is a process in which Knowledge Area?

  1. Project Scope Management
  2. Project Human Resource Management
  3. Project Integration Management
  4. Project Time Management

Answer(s): D

Explanation:

Schedule -> Time Management Easy question



An output of the Validate Scope process is:

  1. A requirements traceability matrix.
  2. The scope management plan.
  3. Work performance reports.
  4. Change requests.

Answer(s): D

Explanation:

Process: 5.5 Validate Scope
Definition: The process of formalizing acceptance of the completed project deliverables.
Key Benefit: The key benefit of this process is that it brings objectivity to the acceptance process and increases the chance of final product, service, or result acceptance by validating each deliverable.

Inputs
1. Project management plan
2. Requirements documentation
3. Requirements traceability matrix
4. Verified deliverables
5. Work performance data

Tools & Techniques
1. Inspection
2. Group decision-making techniques

Outputs
1. Accepted deliverables
2. Change requests
3. Work performance information
4. Project documents updates



The Perform Integrated Change Control process occurs in which Process Group?

  1. Initiating
  2. Executing
  3. Monitoring and Controlling
  4. Planning

Answer(s): C

Explanation:

Monitoring and Controlling Process Group
4.4 Monitor and Control Project Work
4.5 Perform Integrated Change Control
5.5 Validate Scope
5.6Control Scope
6.7 Control Schedule
7.4 Control Costs
8.3 Control Quality
10.3 Control Communications
11.6 Control Risks
12.3 Control Procurements
13.4 Control Stakeholder Engagement






Post your Comments and Discuss PMI CAPM exam with other Community members: