A project manager builds consensus and overcomes obstacles by employing which communication technique?

  1. Listening
  2. Facilitation
  3. Meeting management
  4. Presentation

Answer(s): B

Explanation:

Definitions:
Meeting management techniques. Preparing an agenda and dealing with conflicts. Presentation techniques. Awareness of the impact of body language and design of visual aids. Facilitation techniques. Building consensus and overcoming obstacles.
Listening techniques. Listening actively (acknowledging, clarifying, and confirming understanding) and removal of barriers that adversely affect comprehension.



When does the project team determine which dependencies are discretionary?

  1. Before the Define Activities process
  2. During the Define Activities process
  3. Before the Sequence Activities process
  4. During the Sequence Activities process

Answer(s): D

Explanation:

6.3.2.2 Dependency Determination
Dependencies may be characterized by the following attributes: mandatory or discretionary, internal or external, as described below. Dependency has four attributes, but two can be applicable at the same time in following ways: mandatory external dependencies, mandatory internal dependencies, discretionary external dependencies, or discretionary internal dependencies.
Mandatory dependencies. Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work. Mandatory dependencies often involve physical limitations, such as on a construction project, where it is impossible to erect the superstructure until after the foundation has been built, or on an electronics project, where a prototype has to be built before it can be tested. Mandatory dependencies are also sometimes referred to as hard logic or hard dependencies. Technical dependencies may not be mandatory. The project team determines which dependencies are mandatory during the process of sequencing the activities. Mandatory dependencies should not be confused with assigning schedule constraints in the scheduling tool.
Discretionary dependencies. Discretionary dependencies are sometimes referred to as preferred logic, preferential logic, or soft logic. Discretionary dependencies are established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired, even though there may be other acceptable sequences. Discretionary dependencies should be fully documented since they can create arbitrary total float values and can limit later scheduling options. When fast tracking techniques are employed, these discretionary dependencies should be reviewed and considered for modification or removal. The project team determines which dependencies are discretionary during the process of sequencing the activities.
External dependencies. External dependencies involve a relationship between project activities and non- project activities. These dependencies are usually outside the project team’s control. For example, the testing activity in a software project may be dependent on the delivery of hardware from an external source, or governmental environmental hearings may need to be held before site preparation can begin on a construction project. The project management team determines which dependencies are external during the process of sequencing the activities.
Internal dependencies. Internal dependencies involve a precedence relationship between project activities and are generally inside the project team’s control. For example, if the team cannot test a machine until they assemble it, this is an internal mandatory dependency. The project management team determines which dependencies are internal during the process of sequencing the activities.

Process: 6.3 Sequence Activities
Definition: The process of identifying and documenting relationships among the project activities.
Key Benefit: The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints.

Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Milestone list
5. Project scope statement
6. Enterprise environmental factors
7. Organizational process assets

Tools & Techniques
1. Precedence diagramming method (PDM)
2. Dependency determination
3. Leads and lags

Outputs
1. Project schedule network diagrams
2. Project documents updates



Typical outcomes of a project include:

  1. Products, services, and improvements.
  2. Products, programs, and services.
  3. Improvements, portfolios, and services.
  4. Improvements, processes, and products.

Answer(s): A



Which grid shows which resources are tied to work packages?

  1. Work breakdown structure (WBS)
  2. Responsibility assignment matrix (RAM)
  3. Project assignment chart
  4. Personnel assignment matrix

Answer(s): B

Explanation:

Responsibility Assignment Matrix (RAM). A grid that shows the project resources assigned to each work package.