Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

  1. Uniform
  2. Continuous
  3. Discrete
  4. Linear

Answer(s): C

Explanation:

Decision Tree Analysis. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.

- Can only be used with discrete data.



Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

  1. Update
  2. Preventive action
  3. Defect repair
  4. Corrective action

Answer(s): D

Explanation:

4.3.3.3 Change Requests
A change request is a formal proposal to modify any document, deliverable, or baseline. An approved change request will replace the associated document, deliverable, or baseline and may result in an update to other parts of the project management plan. When issues are found while project work is being performed, change requests are submitted, which may modify project policies or procedures, project scope, project cost or budget, project schedule, or project quality. Other change requests cover the needed preventive or corrective actions to forestall negative impact later in the project. Requests for a change can be direct or indirect, externally or internally initiated, and can be optional or legally/contractually mandated, and may include:

Corrective action—An intentional activity that realigns the performance of the project work with the project management plan;
Preventive action—An intentional activity that ensures the future performance of the project work is aligned with the project management plan;
Defect repair—An intentional activity to modify a nonconforming product or product component;
Updates—Changes to formally controlled project documents, plans, etc., to reflect modified or additional ideas or content.



Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

  1. 100
  2. 120
  3. 1,000
  4. 1,200

Answer(s): A



Which stakeholder approves a project's result?

  1. Customer
  2. Sponsor
  3. Seller
  4. Functional manager

Answer(s): A