The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

  1. Acquire Project Team.
  2. Plan Human Resource Management.
  3. Manage Project Team.
  4. Develop Project Team.

Answer(s): A

Explanation:

Process: 9.2 Acquire Project Team
Definition: The process of confirming human resource availability and obtaining the team necessary to complete project activities.
Key Benefit: The key benefit of this process consists of outlining and guiding the team selection and responsibility assignment to obtain a successful team.
Inputs
1. Human resource management plan
2. Enterprise environmental factors
3. Organizational process assets

Tools & Techniques
1. Pre-assignment
2. Negotiation
3. Acquisition

4. Virtual teams
5. Multi-criteria decision analysis

Outputs
1. Project staff assignments
2. Resource calendars
3. Project management plan updates



At the start of a typical project life cycle, costs are:

  1. low, peak as work is carried out, and drop as the project nears the end.
  2. low, become steady as work is carried out, and increase as the project nears the end.
  3. high, drop as work is carried out, and increase as the project nears the end.
  4. high, become low as work is carried out, and drop as the project nears the end.

Answer(s): A



Success is measured by benefits realization for a:

  1. strategic plan
  2. project
  3. portfolio
  4. program

Answer(s): C

Explanation:

1.4.2 Portfolio Management
A portfolio refers to projects, programs, subportfolios, and operations managed as a group to achieve strategic objectives. The projects or programs of the portfolio may not necessarily be interdependent or directly related. For example, an infrastructure firm that has the strategic objective of “maximizing the return on its investments” may put together a portfolio that includes a mix of projects in oil and gas, power, water, roads, rail, and airports. From this mix, the firm may choose to manage related projects as one program. All of the power projects may be grouped together as a power program. Similarly, all of the water projects may be grouped together as a water program.
Thus, the power program and the water program become integral components of the enterprise portfolio of the infrastructure firm.



Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

  1. Plan Cost Management
  2. Plan Scope Management
  3. Plan Stakeholder Management
  4. Plan Schedule Management

Answer(s): C



A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

  1. Quality assurance.
  2. A stakeholder management plan.
  3. Project team building.
  4. Integrated change control.

Answer(s): D

Explanation:

Process: 4.5 Perform Integrated Change Control
Perform Integrated Change Control is the process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.
Key Benefit: The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.

Inputs
1. Project management plan
2. Work performance reports
3. Change requests
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Meetings
3. Change control tools

Outputs
1. Approved change requests
2. Change log
3. Project management plan updates
4. Project documents updates



Viewing page 49 of 222
Viewing questions 241 - 245 out of 1320 questions


Post your Comments and Discuss PMI CAPM exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!