As part of the Portfolio Communication, the Portfolio Manager analyzes the raw data assimilated from the portfolio process assets and from the stakeholder analysis. This analysis aims to isolate the data that hold value to the receiving audience. Which tool can the portfolio manager use to help him in performing this analysis?

  1. Communication Methods
  2. Elicitation
  3. Stakeholder Analysis
  4. Communication Requirements Analysis

Answer(s): D



The Portfolio Management Office plays an integral role in Portfolio Management and offers support to the portfolio manager throughout the portfolio life cycle. What is the role of the PMO with respect to the portfolio performance metrics?

  1. PMO does not have a role in the development or update of performance metrics; it should only offer support to Portfolio Manager with the needed templates to develop metrics
  2. The Portfolio Manager develops and updates the portfolio metrics and the PMO approves them
  3. PMO should work hand in hand with the governance board to approve the performance metrics
  4. PMO should be prepared to develop new metrics when appropriate and delete or change metrics that are no longer relevant

Answer(s): D



Portfolios include a lot of work and as a portfolio manager you need to keep an eye on the value realization while maintaining the strategic alignment. You are currently in the process of monitoring the portfolio to ensure alignment with organizational strategy and objectives and make governance decisions. What do you expect as an outcome to this?

  1. Portfolio Updates, Portfolio Management Plan updates, Portfolio Reports, Organizational Process Assets update
  2. Portfolio Updates, Portfolio Management Plan updates, Portfolio Reports, Portfolio Process Assets update
  3. Portfolio Updates, Portfolio Management Plan updates, Portfolio Reports, Organizational Process Assets update, Portfolio Process Assets update Portfolio Updates, Portfolio Strategic Plan updates, Portfolio Reports, Organizational Process Assets update, Portfolio Process Assets update

Answer(s): B



Moving from project management to program management and now being appointed as the first portfolio manager in your cyber warfare company, you know you always wondered what happened to the various reports you had to prepare, and the metrics you had to collect. You are working now to determine critical metrics for portfolio management and decided to involve as many people as possible through questionnaires and surveys. You also held some focus groups. The purpose is to:

  1. Ensure the metrics that are collected support the SMART principle
  2. Maximize portfolio value
  3. Represent the vital few rather than the trivial many
  4. Can be gathered with minimal disruption

Answer(s): B



You are the portfolio manager for a large county that comprises much of a major city in your country. The city also has a portfolio manager, and often you meet to discuss proposed initiatives to see if there are any dependencies. In your county, you established an approach to evaluate portfolio components to make judgments regarding their alignment and priority. In doing so, which of the following was especially helpful:

  1. Portfolio strategic plan
  2. Portfolio management plan
  3. Portfolio roadmap
  4. Portfolio charter

Answer(s): B