Working to best optimize resource supply and demand in your telecom company, authorized components are prioritized to help in resource allocation. This means as you work to do so, you need to review the portfolio because:

  1. It provides guidance in terms of recommendations if there are changes in strategy and resource availability
  2. Resource requirements are balanced according to the resource pool
  3. Components are not authorized unless resources are available to support them
  4. Sponsors assess resource requirements and their availability before proposing a component to be in the portfolio

Answer(s): B



As the portfolio manager you have worked to consider the complexities involved of the interdependencies in your programs, projects, and ongoing work. As your portfolio process has been implemented for three years, a key challenge is that senior executives tend to change priorities often even though programs and projects are being implemented. Often these programs and projects are cross-functional, and the result is your process is not coordinated. You recognize there is a need to change, and you met with the Chair of the Portfolio Review Board and have her support for a transparent approach for portfolio standards and prioritization. You should:

  1. Revise the balancing process
  2. Revise the portfolio management plan
  3. Revise the scoring model
  4. Set up a standard method to communicate change

Answer(s): B



As a portfolio manager, you realize the importance of communication for the success of a portfolio. You are now developing the portfolio management plan and are looking for the portfolio current risks status including high risks. Which of the following contains what you are looking for?

  1. Portfolio Management Plan
  2. Portfolio Reports
  3. Portfolio Charter
  4. Portfolio Process Assets

Answer(s): D



You are managing a large portfolio and know that you will need to constantly show the progress and status of the portfolio in meeting. For this you have developed a robust roadmap using BI tools. The Portfolio Roadmap is an important document that is referenced throughout the portfolio life cycle. Which of the following is correct regarding the Portfolio Roadmap purpose and focus?

  1. High-level prioritization mapping of the portfolio
  2. Corresponds to the means to the "to-be" vision
  3. Can be used to influence the portfolio's success
  4. Forecasts how and when the portfolio will deliver value to the organization

Answer(s): A



You have been asked to manage a major portfolio in order to salvage the company and and re-align it with the strategic objectives and goals. You decided to develop the strategic documents and are currently developing the charter. As a portfolio manager, which of the following would be your answer when asked of the purpose for the development of portfolio charter?

  1. Execute portfolio management processes
  2. Authorize portfolio components
  3. Start the development of Portfolio Management plan and all of its subsidiary plan
  4. Develop portfolio structure

Answer(s): A