Free PMI-200 Exam Braindumps (page: 15)

Page 14 of 37

Which term best describes an Agile project's approach to risk analysis?

  1. Regression
  2. Pareto
  3. Qualitative
  4. Monte Carlo

Answer(s): D



In an Agile approach, at which meeting does a team examine the effectiveness of risk responses by conducting a risk audit?

  1. Release planning
  2. Sprint planning
  3. Sprint Retrospective
  4. Daily Scrum

Answer(s): C



According to the Agile Manifesto, which of the following describes the more valued items?

  1. Customer collaboration, following a plan, working software, and individual interactions
  2. Working software, individual interactions, responding to change, and comprehensive documentation
  3. Individual interactions, working software, customer collaboration, and responding to change
  4. Responding to change, individual interactions, processes and tools, and customer collaboration

Answer(s): C



Team velocity is used to:

  1. Measure the percentage of features completed.
  2. Judge productivity within the iteration.
  3. Predict schedules for mature teams.
  4. Give feedback on delivered value.

Answer(s): C






Post your Comments and Discuss PMI PMI-200 exam with other Community members:

PMI-200 Discussions & Posts